Superintendent reports steady progress on renovations, outlines summer programs and recognizes trustee achievement
Summary
Superintendent Dr. Turnell told the board that work on the middle/high school parking lot, cafeteria and high school library is progressing and outlined summer academic and recreational programs; the board recognized trustee Christina Tomlinson for NYSSBA board excellence recognition.
Get email alerts on the Facilities And Programs topic
No spam. Unsubscribe anytime.
During the regular session following the reorganization meeting, Superintendent Dr. Turnell updated the board on construction and summer programming across the district and the board gave public recognition to Trustee Christina Tomlinson for her professional development achievements.
Dr. Turnell reported that the middle/high school main parking lot has been fully milled and existing block curbing removed; crews are installing additional drainage structures. "They're currently working on the installation of additional drainage structures," Dr. Turnell said. He added that the middle/high cafeteria demo is complete and work is under way on the heating and cooling systems and the courtyard areas. "We're really doing well," Dr. Turnell said, describing progress on interior work including HVAC, electrical and general contracting tasks.
The high school library renovation was described as "fully demoed" with about 90% of new walls and sheetrock installed, and Dr. Turnell said the district's director of facilities has been posting weekly rooftop photos to the district construction page so the community can track progress.
On programming, Dr. Turnell said the extended school year began July 1 and runs through Aug. 11. The district's four-week summer academic program is operating at Bayville Primary, supervised by Bill Calandra; a summer recreation program under Marie Fonzo has about 55 campers registered. The high school credit recovery program and driver's education begin July 7, with the driver's education program reporting just over 30 registrants.
The board also made a board recognition: Dr. Turnell announced that Christina Tomlinson was honored in the New York State School Boards Association board excellence recognition program for completing trainings and board-related service activities; the board acknowledged her achievement.
Why it matters: The construction updates indicate projects that affect facilities and student routines in the coming school year; summer-program enrollment numbers provide an early picture of district service utilization. The superintendent emphasized timeliness for window installation and weather impacts on exterior concrete work.
What’s next: The district will continue posting weekly progress photos and will proceed with scheduled program operations through August. The board will formalize committee chairs at the first meetings and follow up on staffing/hiring for special education roles.
Attribution: Direct quotations are taken from the meeting transcript and attributed to Dr. Turnell, the district superintendent, as indicated in the record.