Summary

At the May 21 Development Review Committee meeting, staff presented S26‑012, a 43‑unit, 79‑space redevelopment on Bay Avenue in Ocean City. Committee members raised stormwater and left‑turn safety concerns, asked for a county road improvement sheet and recommended replacing an adjacent sidewalk.

Planning Department staff presented a proposed 43‑unit, 79‑space multi‑family building on Bay Avenue in Ocean City and the county’s Development Review Committee raised multiple engineering and traffic concerns on May 21.

Senior Planning Aide Jake Mericle led the presentation of S26‑012, the Seaspray Redevelopment application, describing the project site and proposed parking. Committee member William Whesper asked about current stormwater conditions; the committee agreed with concerns raised by the project Engineer about a ‘‘bubble‑out’’ discharge inlet that may require redesign or mitigation.

Committee member Patricia Gray Hendricks asked whether the project conforms to the municipal redevelopment plan; the committee asked that that question be addressed in the applicant’s resubmission. Members also agreed with the Engineer’s comment that left turns from the site’s egress driveway could create conflicts and should be evaluated.

The committee recommended replacing the sidewalk in front of the adjacent lot and requested that the applicant provide a separate county road improvement sheet to document any proposed changes to the county‑owned right of way.

No formal vote on the project design or approvals took place during the session; the discussion generated requests for plan revisions and additional documentation that the applicant must supply before final county review.