Board hears masonry repair bid for Giles and a 10‑year facilities plan; funding options debated

Norridge SD 80 Board of Education · March 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board members reviewed a masonry bid for Giles School (base bid $198,470; recommended total with alternates $226,870), discussed a Wold facility study estimating $11.7 million in 10‑year needs and roughly $6.6 million potentially life‑safety eligible, and debated funding choices including a life‑safety bond, levy shifts and CPPRT revenue.

District administrators presented masonry repair needs for Giles School and a multi‑year facilities forecast, and board members discussed how to pay for the work.

Administration displayed photos showing deteriorating brick and ledges and said the issue was not movement of the windows but the surrounding brickwork "starting to bow out," recommending targeted tuckpointing and masonry repair for the east and north facades. Bids opened with a base bid of $198,470; district staff recommended accepting alternates for tuckpointing (alternate items totaling an additional $28,400), for a recommended combined amount of $226,870 to be paid with a mix of district funds and a Giles infrastructure grant. Administrators said an alternate to rebuild the chimney was not pursued because the bid came in for more than $100,000.

The board also reviewed a Wold facility study (presented December 2025) that estimated approximately $11.7 million of work across the district over 10 years, with roughly $6.5 million in years 1–5 and $5.5 million in years 6–10. Staff said about $6.6 million of that total could be life‑safety eligible and might be addressed with a life‑safety bond, but cautioned that state approval of items for bond funding is not guaranteed.

Board members and staff discussed funding routes: pursuing a life‑safety bond (which requires state review), reallocating levy funds (noting constraints on which funds can be levied for building projects), pursuing a referendum, or relying on CPPRT (Corporate Personal Property Replacement Tax) revenue. Administrators said CPPRT receipts are roughly $300,000 per year now but have declined from earlier levels and that some CPPRT must be directed to IMR (items maintenance/replacement) funds. One board member asked whether the district could afford the work without a bond and staff warned it would be difficult because the levy and CPPRT revenue alone would take many years to accumulate the required sums.

No final funding decision was made at the March 18 meeting. Administration asked the board whether it wanted a more detailed breakout showing which 1–5 year projects are life‑safety eligible and what could reasonably be pursued by bond, referendum, or internal funding; board members agreed that a specific breakdown would be helpful for next steps.

Why it matters: The masonry work and broader facilities needs involve substantial capital costs and choices that would affect tax levies, bond obligations and district budgeting. The board signaled interest in getting a detailed life‑safety‑eligible breakdown to evaluate whether to pursue a life‑safety bond, a referendum or another approach.

Administration indicated the masonry/action items would be brought before the board for a formal vote at the next meeting; the board moved into closed session later in the meeting and approved several consent items on return to open session.

Representative quotes from the meeting include administration noting that "the window is not moving, but the brick is moving" when describing the facade issues, and staff saying that roughly $6.6 million of the 10‑year plan could be life‑safety eligible but "if the state doesn't approve it in the bond, then it's not covered."