Norwalk board approves schematic design for new campus and reallocates locally funded initiative money to cover overage

Norwalk City School District Board of Education · March 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved the schematic design phase for the district's new campus and voted to move $331,741.52 from one locally funded account to another to cover a schematic-design overage; the board also confirmed that a previously proposed road to the middle school will not be built and that an on-site bus garage will remain part of the plan.

The Norwalk City School District Board of Education approved the schematic design (SD) for the district's new school campus and reallocated locally funded initiative dollars to cover an SD-phase cost overrun.

Superintendent (identified in the meeting agenda as superintendent) and design staff described the schematic design as the initial footprint for the project; the district will move next into the design-development phase to refine interior spaces and pricing. The superintendent said the footprint remains as previously shown and that the schematic phase confirms overall square footage and program spaces.

Board members discussed a recommended reallocation after the SD-phase yielded an overage of $331,741.52. Trustees said that money was moved from a locally funded outside (LFO) bucket into the locally funded initiatives (LFI) portion to balance the schematic-phase numbers. The board also noted that a road previously considered from Norwalk Middle School across district property to the new building will not be built; the bus garage is planned on site, which reduces outside costs.

A motion to approve item 4.1 (schematic design) was moved and seconded and passed by roll call. The board then approved item 4.2 to reallocate the LFO/LFI funds to cover the $331,741.52 overage; trustees indicated the district remains "in the green" on paper pending firm bid numbers.

District staff said the state is expected to provide approximately $52,000,000 toward the project and that the district's locally funded share remains under active management while more precise contractor bids are solicited. The board and staff emphasized continued coordination with the OFCC liaison and the design team as the project moves into the next phase.

The motions passed on unanimous roll calls as recorded at the meeting.