Milan approves $17.5M budget and awards $41.64M water treatment contract

Village of Milan Council · July 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

On July 6, 2026, the Village of Milan council adopted a $17,504,575 appropriation ordinance for fiscal year 2026–27 and approved a $41,640,000 contract with William Brothers Construction Inc. for a water/wastewater treatment facility; council members also scheduled a July 28 special meeting to set water/sewer rates required by the Illinois EPA.

The Village of Milan council voted July 6 to adopt the FY2026‑27 appropriation ordinance totaling $17,504,575 and to award a $41,640,000 contract to William Brothers Construction Incorporated for the village's water and wastewater treatment facility modifications.

Administrator Steve told the council the package reorganizes the Camden Center into the general corporate fund and highlighted that the water and sewer enterprise funds are the largest financial items. He said the Rainbow Ridge water project is not yet included in this appropriation and that any Rainbow Ridge funding would require a later amendment if the Illinois EPA grant and loan forgiveness are accepted.

"It becomes the council's decision on whether to go forward with the project and under what circumstances," Administrator Steve said, adding staff expects preliminary construction work this fall and that the full construction will span multiple fiscal years.

Councilors questioned revenue assumptions, and Steve said several state formula‑based distributions (for example, the corporate personal property replacement tax) are fixed by population figures. He cautioned the village must adopt a new water/sewer rate structure before Illinois EPA will disburse project funds and noted staff estimates the village will need to generate about $1.4 million a year to service the anticipated loan repayment once the project is substantially complete.

Votes at a glance - 2026 appropriation ordinance: Adopted. Motion made by a trustee and seconded; roll‑call recorded affirmative responses and the chair announced the motion carried. Amount: $17,504,575. (Ordinance number to be assigned.) - Construction contract — William Brothers Construction Inc.: Approved. Motion made, seconded and passed by roll call; chair announced motion carried. Contract base bid plus alternate: $41,640,000 (amount clarified during the meeting).

The council scheduled a special meeting for Tuesday, July 28 at 5:00 p.m. to consider water and sewer rates and related ordinances so the village meets Illinois EPA timing requirements for funding. Steve said staff and legal counsel will prepare ordinance language and the numeric proposals in advance so the council can act that night if a consensus is reached.

Next steps include a preconstruction conference with the contractor and staff work on rate scenarios and any needed ordinance amendments if Rainbow Ridge moves forward.