Council approves final acceptance of water treatment plant; last change order deducts $12,008.77 and one‑year warranty set

Brandon City Council · July 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order No. 10 (a deduct of $12,008.77), accepted final inspection for the water treatment plant after engineer review (AE2S), and set a one‑year warranty start date of May 8, 2026; staff said final payout will be presented at the next meeting.

Staff reported that the contractor completed the water treatment plant and that the engineer of record (AE2S) inspected the work. Staff presented Change Order No. 10, a deduct for $12,008.77, which staff said should be the last change order used to balance quantities and prepare the final payout. Council approved the change order by motion.

Staff then presented the final inspection acceptance form, which sets a one‑year warranty date of May 8, 2026. Council moved and approved acceptance of the final inspection by voice vote; staff indicated that the final payout and any liquidated damages would be reconciled at the next meeting when pay applications are finalized.

Council members asked about the RO (reverse osmosis) system and whether the system reduced softener and salt usage. Staff said they had little subsequent public comment after startup and noted early questions focused on activation timing.

What happens next: staff will present the final payout and any liquidated damages at the next council meeting; the warranty period begins 2026‑05‑08.