Council approves street rehab bid, enters HDBA agreement and clears water change order
Summary
The council awarded a $570,263.10 street rehabilitation contract to Apex Construction LLC, approved a cooperative agreement with the Historic District Business Association, and adopted a $13,453.50 decrease to the water-distribution contract at its July 14 meeting.
Get email alerts on the Procurement Infrastructure topic
No spam. Unsubscribe anytime.
The Natchitoches City Council on July 14 approved several procurement and interlocal actions including a low-bid award for street rehabilitation, a cooperative endeavor with the Historic District Business Association, and a cost-saving change order on a water project.
Street rehabilitation: Councilman PT read Ordinance No. 023 of 2025 and the council awarded the 2025 street rehabilitation project to the low bidder, Apex Construction LLC (Anacoco) at $570,263.10; the other bid from Regional Construction LLC (Natchitoches) was $632,091.50. The council noted three streets were included in the bid package and said work could begin in August if approvals proceed.
Historic district partnership: Councilman Nelson moved and the council adopted Ordinance No. 24 of 2025 authorizing a cooperative endeavor agreement between the city and the Historic District Business Association (HDBA) to have city-funded employees work for HDBA in exchange for services that support tourism and Main Street activities.
Water-distribution change order: The council adopted Resolution No. 60 of 2025 authorizing Change Order No. 1 to the CDE Construction contract for the Bridal Phase 2 water-distribution project. Staff explained specification adjustments — switching from DR7 to DR11 polyethylene pipe (readily available and suitable for municipal 200-psi service) and removing an unnecessary inline backflow check valve — produced a $13,453.50 decrease, lowering the contract from $601,554.20 to $588,100.70.
Councilmembers voted in favor of each item on roll call. Staff said photographs and project updates will be posted on the city’s Facebook page as work mobilizes.