Elberta council approves $412,599 water draw, beach change order and five‑year deficit plan

Elberta Village Council · July 18, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Elberta Village Council on July 18 approved a $412,599 USDA draw payment and related change order for the Lincoln/Bigley water project, authorized several additional project disbursements and change orders including a $6,965 beach improvement change order, adopted a five‑year deficit elimination plan, and approved a formal complaints policy.

The Elberta Village Council on July 18 approved a series of project payments and budget actions tied to the village’s water and beach improvement work and adopted a five‑year plan to eliminate a long‑standing deficit.

The council approved USDA RD 440‑11 draw payment of $412,599.41 to Team Elmer’s for the Lincoln/Bigley phase of the village water project (motion by President Jennifer Wilkins; seconded by Ken Holmes). The board also approved USDA Change Order No. 3, which reduced the contract price by $25,114.15 (motion by Pro Tempore Emily Votruba; seconded by Ryan Fiebing). Roll calls for both actions were recorded as all ayes.

Council members approved DWRSF request No. 8 for $87,470 to Team Elmer’s for water‑service work performed Dec. 31–June 30 on Lincoln and Bigley (motion by Votruba; seconded by Wilkins). Separately, the council authorized Team Elmer’s to repair and patch the end of Crapo Street at a budgeted FY25 cost of $15,650 (motion by Ryan Fiebing; seconded by Emily Votruba); that proposal was described in the meeting as budgeted for FY25 and passed by roll call.

On the village’s Elberta Beach Improvement Project (MNRTF20‑0013), the council approved Change Order No. 2 adding stone and amending a section of walkway to cover exposed rock, with a net increase of $6,965.30 and a contract time extension to Oct. 31. Minutes note dune grass planting cannot be done until mid‑September and that new bathrooms and a pavilion are expected in August.

The council also adopted Policy #2024‑003, establishing a protocol for filing and responding to official complaints; the policy was reviewed in advance by the village attorney (motion by Wilkins; seconded by Ryan Fiebing). Finally, the council unanimously adopted Resolution #2024‑005, the FY 2022–23 Five‑Year Deficit Elimination Plan, which the minutes say anticipates the deficit being paid off in FY26/27, possibly sooner (motion by Emily Votruba; seconded by Ken Holmes).

Routine financial business also moved on consent: accounts payable of $71,550.07 were approved and payroll approvals were handled in separate roll‑call votes where Wilkins and Votruba recused themselves from portions of the payroll due to declared conflicts of interest.

The council did not record extensive debate on the substantive motions; all listed motions passed on roll call with votes recorded in the minutes. The meeting adjourned at 8:29 p.m.