Raleigh explains 'typical' plan approval to speed townhome permits
Summary
City staff described a voluntary 'typical' approval that pre-approves architectural and structural plans (TYP number), which applicants can reference at building-permit time to shorten review cycles; the typical does not substitute for site-level zoning review and may not be applied across different developments without a new typical number.
Get email alerts on the Typical Program topic
No spam. Unsubscribe anytime.
Erin Becton, a residential plans reviewer with the City of Raleigh, detailed the city’s "typical" approval program as a tool to expedite repetitive building reviews for townhome projects. Under the program, applicants submit architectural and structural plans for approval before applying for building permits; once approved the set receives a typical number (TYP) and an approved-plan attachment that can be associated with subsequent building permits for identical floor plans.
Becton said the typical is optional, is not itself a building permit, and does not eliminate site-review or zoning checks. "The typical is basically like the building in a vacuum subject only to building code review," a staff member added, noting that when the typical is placed onto a site, planning and zoning requirements (ASR/SPR) may still be triggered. Becton said that a typical remains valid for the project and does not expire, but that applicants must apply a new typical number if they want to reuse the same plan set on a different development or a materially different layout.
Intake and customer-service staff walked through practical submission steps: a typical application is emailed to the city's commercial-building intake address (staff noted the email may change), approved plans and a spreadsheet of square-footage details will be attached to the typical case, and applicants must include elevation pages on later building-permit submissions so zoning can confirm heights and setbacks.
Staff cautioned that applying a typical before site approvals is possible but carries risk because the typical does not guarantee site-specific entitlements. "You can apply for a typical whenever, but you just can't apply it to when you do your building permits" without coordinating site-level approvals, one reviewer said. The city encouraged applicants to consult intake staff if they are unsure when to start the typical process.