Commission discusses Riverside bridge funded by federal appropriation and local match needs
Summary
Commissioners reviewed a $1,020,000 direct federal appropriation for a Riverside bridge and discussed project scope, design (cast-in-place culvert), potential extra county costs if bids exceed the appropriation, and an MOU with the city of Riverside to oversee work.
Get email alerts on the Bridge Funding topic
No spam. Unsubscribe anytime.
Commissioners and county engineering staff discussed a direct federal appropriation of $1,020,000 for a Riverside bridge project and what local costs the county may need to cover. County staff described the structure as a cast-in-place culvert that must be buried to protect substrate and fish habitat; "It's actually a cast in place culvert," an engineer said.
The commission noted the appropriation likely will not cover every possible bid scenario. "Let's just say the bridge comes in at, million 400,000. We're only getting 1,020,000," one commissioner asked; staff confirmed the county would need to identify additional funds if the final bid is higher. Commissioners discussed a memorandum of understanding with Riverside so the county can oversee the project while the city retains final ownership and administration of the work.
Why it matters: the appropriation is a one-time federal award that accelerates a long-discussed local project but may require local matching funds or additional county spending to complete the full scope. Commissioners raised whether any of the appropriation can be used for an adjacent bypass (Sugar Farm Road) or other local roadway work; staff said those questions will be clarified once paperwork arrives and by consulting ALDOT and project engineers.
What's next: staff will pursue funding and scope clarifications, coordinate with Riverside on an MOU, check federal procurement and eligible-cost rules, and return with recommendations; no final construction contract was approved during the work session.