Early council approves change order and $10,212.59 pay application for DD-59 project

City Council of the City of Early, Iowa · November 5, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Early City Council on Nov. 5 accepted Change Order #5 (net +$3,316.40) and approved Pay Application #9 to Empire Excavation for $10,212.59 tied to the DD-59 drainage project; ISG briefed the council and set a Nov. 12 special meeting for landowner claims.

The Early City Council on Nov. 5 approved a $3,316.40 net change to the contract for the DD-59 project and authorized a $10,212.59 pay application to Empire Excavation, the council record shows.

Rachel with ISG presented the monthly engineering report and told the council that landowners were mailed notice of a Special Meeting set for Tuesday, Nov. 12 at 7 p.m. "Before damages can be paid, landowners need to submit to the council in writing their claims prior to the November 12th Special Meeting," Rachel said. She also recommended that the contractor replace the full panel damaged on 3rd Street and that all supplier bills be submitted before the project is closed out.

Councilor Becky Blackman moved to accept Change Order #5, which the record lists as a net change of $3,316.40; Councilor Brian Pickhinke seconded, and a roll-call vote was unanimous in favor (Scadden, Madden, Langner, Pickhinke, Blackman). Later, Councilor Brandon Scadden moved to approve Pay Application #9 to Empire Excavation for $10,212.59; Councilor Blackman seconded and the motion passed on a unanimous roll-call vote.

The council did not record any dissent and directed that landowner claims be submitted in writing prior to the Nov. 12 special meeting; no timeline for final project closeout beyond that requirement was provided in the meeting record. The City Attorney was not present at the session.