Union City Council approves sinkhole repair, easements and routine land-use actions

Union City Borough Council · August 13, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At its Aug. 13 meeting, Union City Borough Council unanimously approved a $22,295 contract to repair a sinkhole and associated pipe work in Municipal Lot #1, retroactive easements for 104 East High and purchase of a small parcel for a gazebo project, plus approval of MMO, a subdivision and a kayak/canoe launch easement funded by state and nonprofit grants.

Union City Borough Council on Aug. 13 approved multiple infrastructure and land-use actions, including a $22,295 contract to repair a sinkhole at Municipal Lot #1, retroactive easements related to 104 East High, approval of the borough’s minimum municipal obligation for pension funding, subdivision sign-off for West High Street properties, a $500 parcel purchase for a gazebo project, and an easement for a kayak and canoe launch at the American Legion ball field.

Streets Supervisor Bob Phillips reported that a sinkhole had developed at Municipal Lot #1 where a 24-inch clay tile had failed; engineer recommendations included replacing tile, reconnecting pipes, installing a larger catch basin and replacing approximately 10 feet of pipe. Two contractor estimates were presented: Mansfield at $22,295 and McLallen Construction at $23,450; council voted to contract Mansfield for $22,295 and agreed the borough would provide a truck during the project.

Council approved a retroactive easement with property owner Anthony Hickey at 104 East High Street to allow the borough to install a catch basin and to connect it by pipe to a PennDOT-installed basin. Under the agreement the property owner will dig and maintain a ditch and install the connecting pipe; the borough will accept responsibility for the two catch basins and about 60 feet of pipe.

Borough Manager Cindy Wells presented the 2025 MMO figures: $48,029 required for the non-uniform pension and $0 for the police pension; the council approved the municipal obligation as presented. The council also approved a subdivision combining a portion of 92 West High Street with 88 and 90 West High Street after Erie County Planning approval, and approved a $500 purchase of a small parcel adjacent to Municipal Lot #3 for a gazebo project pending survey and solicitor paperwork.

Council also approved an easement with the American Legion to install and maintain a kayak/canoe launch along French Creek; the project will be funded by the Pennsylvania Fish and Boat Commission and the Pennsylvania Environmental Council. All recorded motions on these items carried unanimously.