Board approves multiple construction contracts, softball field GMP, separated purchases and amends public-comment policy (all votes 7'00)

New Albany-Floyd County Consolidated Schools Board of Trustees · April 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a regular board meeting trustees approved construction-management contracts and a $6.2 million GMP for the Floyd Central softball field, separately approved chiller warranty, Chromebooks and projectors, and amended public-comment policy; all recorded roll-call votes were unanimous.

The New Albany-Floyd County school board approved a slate of capital and procurement actions and amended its public-comment policy during a single regular meeting; all recorded roll-call votes on those formal items were unanimous (7'00).

Facilities staff recommended construction-manager selections for three projects: Skillman Construction for Fairmont (preconstruction fee $46,850 and a construction-staffing lump sum of $463,972 with 1.85% overhead), Core Construction for Prosser (preconstruction $15,000; staffing $456,741; 2.5% fee), and Core Construction for Floyd Central (preconstruction $9,000; staffing $237,249; 2.5% fee). Trustees voted to approve the recommended construction-management contracts.

The board also approved engaging Shireman Construction Group to provide construction-management advisory services for gym renovations at New Albany and Floyd Central at a combined fee of $239,500. The work includes bleachers, wood floors, sound system upgrades and HVAC improvements.

District staff recommended awarding a Guaranteed Maximum Price (GMP) for the Floyd Central softball field project. Staff cited a GMP of $6,204,637 and noted some value-engineering items remain pending that could reduce the final price. Trustees approved the award on a 7'00 vote.

Earlier in the meeting trustees separated three consent items for discussion: an extended chiller warranty and preventative-maintenance agreement, Chromebook purchases, and classroom projector purchases. Facilities and technology staff explained the lifecycle and breakdown risks for chillers and the four-year device replacement cycle for Chromebooks; staff said limited trade-in credit is available. The board approved those three items by motion and roll-call vote.

On policy, trustees amended Policy 0167.3 (public comments at board meetings) to retain the current structure but require that a prepared enforcement/read-aloud statement (the "red" language discussed during the meeting) be read to speakers; board members also clarified a wording correction from "public meeting" to "a meeting held in public." The motion to keep the existing policy with the added read-aloud language passed 7'00.

The board also approved technical corrections to Policy 8505 concerning student-account notifications and procedures by unanimous vote.

Votes at a glance (recorded items in meeting):

- Separated consent items (chiller extended warranty/preventative maintenance; Chromebook purchases; classroom projectors): Approved, vote 7' 0. - Construction-management contracts (Fairmont, Prosser, Floyd Central): Approved, vote 7' 0. - Construction-management services for gym projects (Shireman Construction): Approved, vote 7' 0. Fee: $239,500. - GMP award: Floyd Central softball field (Core Construction): Approved, vote 7' 0. GMP cited: $6,204,637 (some value-engineering items pending). - Policy 0167.3 amendment (retain current policy, add read-aloud enforcement language and minor wording fix): Approved, vote 7' 0. - Policy 8505 technical corrections: Approved, vote 7' 0.

Board members said the approvals will allow administrators to proceed with contracting and project oversight. Several trustees requested continued reporting on budget-to-actual costs and updates on value-engineering choices for the softball field.