Commission approves courthouse roof agreement with TCS; elevator battery-backup scheduled
Summary
After contractor updates on ADA parking, elevator diagnostics and roof timeline, the commission approved the roof contract with TCS and discussed Otis-supplied battery-backup pricing and service options; commissioners asked staff to confirm scheduling and local service options.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Granite County Commission approved an agreement with TCS Northwest to proceed with the courthouse roof project after TCS and ACS representatives reviewed project timing, ADA parking work and elevator battery-backup options.
Terry Moreland of ACS explained the ADA parking pour and that Otis reduced pricing for the elevator battery-backup, which the county accepted; contractors said they expect to pour concrete and substantially complete ADA parking work by the end of next week. The elevator vendor and county staff discussed diagnostic tools, lead times and options for alternate local service providers (for which the county would need to purchase a diagnostic tool to allow non-Otis firms to service proprietary components).
Commissioner discussion focused on lead times for windows, plumbing and asbestos abatement; the board approved moving forward with the roof contract and authorized electronic signature. Commissioners asked the project superintendent and administration to coordinate schedules and provide contact information for county staff.