Corinth planning board conditionally approves sketch plan to subdivide 16 William St, sets fire-safety conditions
Summary
The Corinth Planning Board on Oct. 6 conditionally approved a sketch plan to split 16 William St into three lots, granting a waiver of the two-street-connection rule while requiring an on-site hydrant, expansion of a common driveway to meet NYS fire apparatus standards, engineering reviews and hydrant flow testing at the applicant's expense.
Get email alerts on the Land Use Subdivision topic
No spam. Unsubscribe anytime.
The Corinth Planning Board on Oct. 6 conditionally approved a sketch plan to subdivide 16 William St (Tax Map ID 59.81-1-28) into three lots, but placed multiple fire-safety and engineering conditions on the project.
Chairperson Phyllis Morreale moved to declare the application (PB-2025-0003) a minor subdivision and the board approved that motion unanimously. The board then voted to grant a conditional waiver under Village Code Section 435-29 from the two‑street‑connection requirement of Section 435‑22(F), subject to three specific conditions: the applicant must install a fire hydrant on the property at a location to be determined by the Fire Chief and the applicant; expand the proposed common driveway to conform to fire apparatus access requirements under the New York State Fire Code; and ensure access and the driveway conform to the Fire Department's standards.
The board also found the sketch plan application complete and conditionally approved it, tying approval to additional requirements in Article VI of the Subdivision Code. Those conditions require the applicant to address all general requirements and design standards on the preliminary plat or explain why certain standards cannot be met, obtain expert/engineered advice on site limitations, and have the village engineer review the project generally. The board listed specific engineering concerns to be resolved, including: water availability for emergency response; how expanding the common driveway to a fire apparatus road will affect proposed sewer and water line placement and minimum setbacks; and whether adding a hydrant and converting the driveway will deliver adequate emergency response.
Board members and staff expressed concern about the narrow width of William Street (approximately 14 feet), traffic and congestion from additional garbage/recycling receptacles, and the need for an emergency vehicle turnaround. The board discussed a possible condition requiring the applicant to provide a dumpster to avoid placing more trash containers on the street. The board also required that a hydrant flow test be conducted at the applicant's expense and supervised by the DPW superintendent.
Project assistant Michael Bouchard told the board he believed there was precedent for the subdivision because, in his view, a previous approval had been granted and the plans had not changed. Code Enforcement Officer Neil Hepner said he would request written input from the DPW superintendent about water and sewer feasibility and recommended the board grant sketch-plan approval based on the materials submitted for the sketch stage.
The board recorded all formal motions as passing on unanimous voice votes ('all in favor — aye'). No start date for any required follow-up studies or installations was specified during the meeting. The board did not set a date for its next meeting and adjourned at 7:03 p.m.