Commission waives first-month damages for new waste hauler after rollout problems; motion passes 3-1
Summary
After presentations from city engineering staff and Coastal Waste & Recycling, the commission approved waiving the first 30 days of performance damages (August) — $70,450 — citing implementation issues during the contractor's rollout; the motion passed 3-1 with Commissioner Wimberley voting no.
Get email alerts on the Solid Waste Contracts topic
No spam. Unsubscribe anytime.
The engineering committee considered disputed performance damages assessed under the county's new waste-hauling contract with Coastal Waste & Recycling, which assumed all three collection zones on Aug. 1 and encountered implementation issues.
Engineering Director Dr. Malik described the invoicing and assessment process for missed collections, cart deliveries and other service failures; staff and Coastal then reviewed monthly invoices line by line. Coastal representatives said early charges were driven largely by cart-delivery and inventory problems and by data mismatches between legacy route software and Coastal's systems. Coastal said it has since reduced assessed fines significantly through operational adjustments.
City staff recommended waiving the first 30-day (August) performance damages to resolve the dispute; the amount stated in the meeting for that waiver was $70,450. Coastal accepted the adjustments for September and October after reconciliation. The commission voted to approve the director's recommendation; the motion carried 3-1 with Commissioner Wimberley recorded as the lone no vote.
The commission directed staff to continue working with Coastal to reconcile invoices and apply credits against future invoices as appropriate.