Lubbock ISD approves change order after unexpected underground infrastructure, adding roughly $150,000 to demolition work
Summary
District staff said unexpected underground infrastructure required fuller excavation on recent demolition projects, increasing scope by about $90,000 at one site and roughly $60,000 at another; the board approved the change order unanimously.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Lubbock ISD trustees approved a change order to complete demolition work after staff discovered previously unknown underground infrastructure at project sites, increasing the district’s scope and cost for the work.
Dr. Anderson explained to trustees that the demolition required complete excavation where previously only partial work had been planned; staff estimated the added scope raised costs by about $90,000 at one site and a little over $60,000 at another. Dr. Anderson identified the demolition contractor as Construction Consultants and clarified that the vendor is separate from the district’s architect contract.
Trustees asked follow-up questions about the contractor and scope before a motion to approve the district construction purchase (the change order) was moved and seconded. The presiding officer called for a show-of-hands vote and recorded the motion as carrying unanimously, 5-0.
The board then recessed to an executive session later in the agenda; the change-order approval authorizes staff to proceed with the demolition work as presented.