Council hears Scribner Street storm-sewer update after engineering omission; Oct. 10 completion targeted
Summary
City staff reported a revised plan to install multiple catch basins at the Summit/Scribner/Cedar intersection to correct storm-water flow; the state is pursuing the engineer's Errors & Omissions coverage and the city may incur a small cost if insurance does not cover corrections. The official project completion date is Oct. 10, 2025.
Get email alerts on the Stormwater Infrastructure topic
No spam. Unsubscribe anytime.
City presenter Johnson told the Spooner City Council on July 1 that revised plans to fix storm-water flow affecting N. Summit Street and the intersection of Hwy K, Summit and Cedar call for multiple new catch basins to collect runoff.
Johnson explained that a contracted engineer’s plan omitted an elevation change and lacked sufficient inlets at the intersection; the state is pursuing the engineer’s Errors and Omissions insurance. Johnson said the city would have only a small amount of cost exposure if the engineer’s E&O coverage does not resolve the claim. The official project completion date is Oct. 10, 2025, but staff said they hope to finish before the school year starts.
Council discussion focused on the technical correction (catch basins and curb-line realignment near Triangle Park) and on settling any costs after insurance and E&O processes conclude. No formal vote was recorded on cost allocation during the meeting.