Cabot reports near-complete practice pavilion, Pre-K site progress and security upgrades funded by grants and bonds

Cabot School Board · September 17, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff told the board the practice pavilion is about 95% complete with turf and landscaping under way, Pre-K metal buildings are expected in October, and security upgrades paid with a $506,800 School Safety Grant and $1.2 million in bond proceeds have been installed; the district applied for additional grant funds.

Michael Byrd told the Cabot School Board that the district’s practice pavilion construction is roughly 95% complete and that landscaping will begin next week while turf is being installed. Byrd said Pre-K metal buildings are expected to arrive in October and the Pre-K North slab is complete. The district’s carpet project is complete except for Fine Arts and CAO spaces, and a bid opening for the special programs annex is scheduled for Thursday.

Byrd also reported the district used a $506,800 School Safety Grant and $1.2 million from a second-lien bond sale for security projects. The district installed electronic access controls, visitor-management systems, window covers for classroom doors, classroom locks, exterior-visible room numbers and touch-bar exit devices where needed. Byrd said the district has applied for additional grant funds to continue safety work.

Byrd noted turf is being removed at the fieldhouse to start a locker-room expansion; the board received the facilities updates as information.