Sherwood advances MIEX water‑treatment pilot, searches for Well #7 amid system upgrades

Village of Sherwood Village Board · July 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The village ran a MIEX ion‑exchange pilot to reduce organics, pursued test wells for Well #7, advanced pump/lift‑station fixes and approved the STH‑114 water main extension while utility staff planned a 12‑inch force main to relieve lift‑station load.

Sherwood’s utility officials moved forward on several water‑system issues in 2006: a MIEX pilot to reduce total organic carbon (TOC) and sulfides, search for a dependable Well #7 site, a temporary acid feed installation at Well #5, and extension of the STH‑114 water main.

MIEX pilot: McMahon Associates and contract operator Midwest Contract Operations ran a MIEX ion‑exchange pilot in May to assess removal of TOC and sulfides. Preliminary results cited in board materials reported roughly 90% TOC removal in some runs; technical interruptions extended the test schedule and a final report was expected after additional analysis. Commissioners discussed pilot configurations and recommended an "800" design for future work pending DNR discussions.

Wells and treatment: Engineer Gary Rosenbeck and Van Lieshout reported test‑well quotes and drilling plans for potential Well #7 sites; one test site was temporarily inaccessible due to wet ground conditions and drilling delays pushed property closing dates tied to the well purchase. The utility also pursued a temporary acid feed at Well #5 to reduce raw water pH to the aerator and examined MIEX/ozone combinations.

Distribution upgrades: The board approved the STH‑114 water main extension and certified partial payments to contractors; utility staff and engineers discussed a proposed 12‑inch force main from Lift Station 3 to the wastewater treatment plant to alleviate future capacity issues. Commissioners also approved limited chemical additions (ferrous chloride) at the High Cliff lift station to address odors and headworks heating/ventilation upgrades were previously approved.

Why it matters: The measures aim to improve water quality and system reliability as Sherwood grows. Pilots and force‑main planning are forward‑looking engineering steps; test‑well results and regulatory approvals will determine long‑term paths and funding needs.

Next steps: Final MIEX pilot reporting, DNR approvals for pilot scale changes, continued testing at potential Well #7 sites, and engineering proposals for the force main were identified as upcoming actions.