At its July 2 meeting the council awarded a construction‑management task order for the West Main Street pedestrian corridor, approved public safety roof replacement and related envelope‑inspection services, authorized property negotiations for Highway 140 parcels, and approved an annexation/rezone request and other routine items.

The Canton mayor and council approved a package of contracts and land‑use actions during the July 2 meeting, including a contested award for construction management on the West Main Street pedestrian corridor and the selection of an inspection firm for the public safety roof replacement project.

Task Order 9 — Practical Design Partners LLC (West Main Street Pedestrian Corridor): Council approved awarding Task Order 9 to Practical Design Partners LLC for construction management services in an amount not to exceed $258,370 after a discussion about the contract’s scope and cost. Council members questioned the number of proposed site visits and whether some inspections could be handled internally; staff said complexity and extensive utility coordination (including Georgia Power relocations previously contracted and anticipated utility charges) drive the higher cost. The motion passed with one recorded no vote; the remainder voted aye.

Public safety roof replacement contract: Council approved a roof replacement contract for the public safety building; staff said the contractor extended the labor warranty from two to five years and included an owner’s contingency of $76,000 that requires city approval before use. The motion to approve the contract carried unanimously.

Inspection and building‑envelope assurance services (Intertek/Architectural Testing Inc.): Council approved a separate contract with Intertek for inspection and building‑envelope assurance services not to exceed $28,815. Staff recommended Intertek over a lower‑frequency inspection proposal because Intertek’s scope includes preconstruction coordination to mitigate ongoing leaks and more frequent site visits during construction; the vote was unanimous.

Other actions: Council approved a resolution to abandon Lee Street and authorized the mayor to sign a quitclaim deed to Cherokee County; it also authorized the city manager to negotiate and settle parcels related to the Highway 140 projects to streamline property acquisitions (council indicated about 45 parcels). Several rezoning and conditional‑use items were set for future public hearings or approved on consent. Most motions were approved unanimously unless noted above.

Full votes and next steps: where council set public hearings or actions (for example the RZON2604‑010 rezoning), staff will return with recommended conditions and a formal action item at the scheduled meeting dates noted in the staff reports.