David E. Ross recommended for Richmond 210 Lift Station project; later change order trims contract

City Council of the City of Richmond, Missouri · July 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City accepted Olsson's recommendation to award the 210 Lift Station and stormwater equalization basin expansion to David E. Ross Construction. Subsequent change-order review reduced the contract by $5,740 to $769,060.

The City of Richmond received engineering recommendations from Olsson and approved a low-bid award to David E. Ross Construction for the 210 Lift Station and stormwater equalization basin expansion (initial contract amount reported $774,800). The award came after Olsson’s low-bid review process and a recommendation at the Oct. 22 meeting.

At a later council meeting the city and engineer reviewed bid items and proposed contract adjustments. The Council approved a change order that reduced contract bid items by $5,740, lowering the contract price to $769,060. The change reflected agreed deletions and a single added item negotiated with the contractor following review of scope and unit prices. The engineer (Olsson) retained oversight of the design/construction phase and will administer change orders and payment applications during construction.

Vote and next steps: The initial notice of award and contract approval were accepted on Oct. 22 (roll-call recorded in the minutes). The change order was approved on Nov. 12 by unanimous council action; staff will proceed to finalize the contract and begin construction mobilization per Olsson's schedule.

The project expands lift-station capacity and adds a stormwater equalization basin to address recurring SSO and capacity issues in the 210 basin area. The contract includes design, construction administration and observation per the original work order.