The Weyauwega Common Council approved replacement of a remote HMI screen and a UV system upgrade at the wastewater treatment plant, authorizing up to $11,145.96 from the Wastewater Maintenance budget and $1,025.22 for the UV work.
Get email alerts on the Wastewater Infrastructure topic
No spam. Unsubscribe anytime.
The Weyauwega Common Council on April 15 approved two maintenance upgrades at the city’s wastewater treatment plant, including replacement of a remote human-machine interface (HMI) screen and a UV system upgrade.
Police Chief Brandon Leschke described the HMI replacement — a remote computer screen located by the tanks that lets staff adjust operations on site — and said vendor costs would be about $8,500 with additional travel and on-site service charges, for a total not to exceed $11,145.96. Council member Pat Gorchals moved to approve the HMI update and Chris Gunderson seconded; the council voted to fund the work from the Wastewater Maintenance budget and the motion carried with five ayes and zero nays.
Earlier in the meeting the council approved a separate UV upgrade at the WWTP at a cost of $1,025.22. Both items were presented as routine public works maintenance to improve on-site control and reliability.
The approvals authorize staff to proceed with purchasing and installation under the specified budget lines; the council did not identify a contractor in the meeting minutes and did not schedule further public hearings on the items. The upgrades are intended to reduce staff travel time to the plant’s control room and to maintain disinfection functions at the treatment facility.