The commission approved CUP 25004 and recommended approval of an amended development agreement (Bill 388) for Sherwood Village, a 293-unit duplex-style workforce housing project, after extensive discussion on traffic, parking, emergency access and a contested applicant request to use a lower water-rights metric than city code.

The Fernley Planning Commission approved a conditional use permit and recommended an amended development agreement for a 293-unit workforce housing development known as Sherwood Village, following lengthy staff presentations, technical Q&A and public comment that highlighted traffic and water-rights concerns.

Staff's presentation (Tristan Rodriguez) described CUP 25004 as a request for duplex-style multifamily development on approximately 26.47 acres in the MDR-14 district, with an estimated density of about 11.07 dwelling units per acre (below the 14 DU/acre maximum). Staff concluded all six required findings could be made, recommended approval and asked the commission to add a condition requiring recordation of a reversion to acreage prior to building permits.

Applicant counsel Garrett Gordon and developer representatives described the project as an infill, amenity-rich, gated rental community targeted at workforce households (50'70% AMI) with unit sizes between roughly 944 and 1,500 square feet, internal sidewalks, and recreational amenities. The developer said the project would construct Fremont Street frontage improvements, Vine Street emergency access improvements and on-site infrastructure at the developer's expense.

Commissioners pressed the applicant and staff on traffic impacts at the Fremont Street intersection, emergency access and buffer widths. The applicant's engineer (Dave Snellgrove) and traffic consultant reported that a traffic impact analysis had been performed, that AM peak level of service remains a B and PM a C with the project, and that required Fremont improvements would be implemented through the development agreement. The commission temporarily recessed to locate the study before resuming.

Multiple neighbors urged the commission to consider traffic, parking overflow and neighborhood impacts; speakers said Fremont Street currently experiences turning-lane congestion and objected to adding hundreds of residential units with limited egress.

A major point of debate came during the development-agreement discussion (Bill 388): the applicant asked that the city use the 2022 Water Master Plan's average residential connection demand (344 gallons per unit per day) to calculate water-right dedication requirements rather than the city's current code standard (which the applicant said equates to a higher per-unit dedication cost). The developer proposed a two-year performance-bond mechanism to guarantee the city's water-right needs would be met if actual usage exceeded the master-plan estimate. City staff and the planning director advised against changing the city's standard, and several commissioners expressed concern that making an exception would set an undesirable precedent. The city attorney confirmed the commission has the authority to recommend the change but noted council direction favors strict application of the code.

After debate, the commission approved CUP 25004 (motion by Commissioner Flores, seconded and carried 6-0) with the added reversion-to-acreage condition. The commission also recommended approval of Bill 388 as presented in staff materials (6-0 vote). Council will review the development agreement and any proposed water-right deviation.

Next steps: record reversion to acreage before building permits, execute the development agreement obligations (Fremont Street improvements, right-of-way acquisition procedures, emergency access), and continue coordination on water-rights and infrastructure fees at council review.