Board reviews easement negotiations and tract-by-tract workarounds; Tract 20 remains sticky
Summary
Project staff reported 25 easement agreements signed and 24 still outstanding, outlined parcel-specific workarounds to avoid acquiring full property title, and warned that Tract 20’s retaining wall poses limited options without owner agreement.
Get email alerts on the Easement Acquisition topic
No spam. Unsubscribe anytime.
Project staff told the board the effort to secure easements for a downtown streetscape project is advancing but remains incomplete, with staff reporting “25 signed, 24 outstanding” in the status matrix and recent progress on parcels including Branson, Star Theater and Wendy’s.
Project lead (S10) walked members through the color-coded tracker and said staff expect more movement in the coming days: “We picked up Branson, Star Theater over the last 2 weeks, and we also picked up Wendy's,” he said. He described groups of properties that could be bundled and noted active attorney engagement on several parcels.
Legal counsel explained the difference between condemning full property title and acquiring easement rights, telling the board that ‘‘we are not condemning an entire lot. We are requesting the easement…We are not in any way in a position to condemn all of these properties or to pay the fair market value of the entire property. The property would remain with the owners. They just would be compensated for the value of what we would be taking, which is an easement right.’’ (S8)
Project designer Jeremy (S1) described tract-level workarounds — shifting easement alignments, narrowing sidewalks, removing some landscape improvements and relocating drive entrances — and said many red tracts could be moved into yellow or green with modest redesigns. He cautioned that Tract 20, where a 6-foot retaining wall exists, offers fewer options: “I don't have a workaround on '20,” he said.
Board members raised concerns about timing, precedent and cost. One member warned that broadly initiating condemnation could set a precedent the district might not want; counsel responded that condemnation in this context would be limited to easement rights and determined by appraisal.
Staff stressed a parallel approach: continue owner outreach and legal negotiation while authorizing limited redesigns for the most obstructive tracts so the overall project can move forward. The board approved a motion authorizing redesign work at a fee not to exceed $25,000 to support that strategy.
Staff plans to continue outreach and bring updated easement and design status back to the board at its December meeting.