Board authorizes $54,300 for repairs to dry detention areas on Wirsfield Road
Summary
The Greenwood Stormwater Board authorized work on two dry detention areas along Wirsfield Road with a combined contractor estimate of $54,300 and directed the stormwater superintendent to sign the agreement.
Get email alerts on the Wirsfield Road Repairs topic
No spam. Unsubscribe anytime.
The Greenwood Stormwater Board authorized repairs to two dry detention areas on Wirsfield Road after staff presented contractor estimates totaling $54,300.
A staff presenter said the same contractor that worked on similar fixes last year provided the estimate and recommended the board authorize the stormwater superintendent to sign the contract. The board moved, seconded and approved a not-to-exceed amount for the combined repairs.
Board members clarified the repairs are for the north side of the road, near Summerfield, and not an extension of city sewer lines into private property. The funding was described as available in the appropriate operations/construction line in the stormwater budget.
Next steps: staff to finalize contract documents and schedule the work; the superintendent is authorized to sign the agreement on the board—ehalf.