Marthasville reports paving finished on four streets; Fifth Street widening awaits utility work
Summary
The board was told NB West completed paving on four streets, including bridge repairs; Fifth Street will be widened after Ameren UE relocates poles, Mayor David Lange reported.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Mayor David Lange told the Board of Aldermen on Nov. 26 that NB West completed paving work on four streets within Marthasville and that crews paved over several rough bridge sections.
He said North Street was paved to the dead end, South Street to where Pecan starts, and that crews completed two additional streets and bridge surfaces. Fifth Street is identified as ready to be widened but remains contingent on Ameren UE moving utility poles before work can begin.
The update was provided as an informational report; no formal action was recorded other than recognition of the work completed.