Library board shifts contingency, approves transformer pad and mural spending

Ripon Library Board · May 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Ripon Library Board voted to move renovation contingency funds, approve payment for a new transformer cement pad needed for a June 8 cutover, authorized a small architect reimbursement and approved up to $4,000 of Carnegie funds for a children's mural.

The Ripon Library Board voted to transfer money into a contingency line and to pay for a new concrete pad required for a transformer installation, the board’s director said. "We have officially heard word that that will be June 8 for the transformer installation and electrical service cutover," Library Director Nizzie Bell told the board, and Allied (the electrical contractor) concluded a new transformer and special reinforced pad are required.

The board debated sources of funds and agreed to shift roughly $1,814 into contingency after subtracting a $5,000 donor credit to cover the additional work on the renovation. A committee member moved to transfer the money "out of the renovation fund and move it into the contingency fund," and the motion was seconded and approved by voice vote.

Board members then approved payment of an invoice for $9,864 to cover site preparation and the special cement pour for the transformer pad so Allied can proceed with the June cutover. The board also approved a $145.30 invoice to reimburse an architect/consultant for a site visit.

Separately, the board authorized spending from a $10,000 Carnegie Foundation donation to fund a mural in the children’s wing. Children’s librarian Linda Kramer proposed hiring local muralist Katie Lang to create an approximately 10x10 mural; Bell said the estimate for the work is about $3,700 and recommended placing a $4,000 cap. "We would put a cap on it — up to $4,000 on this mural project," a board member motioned; the motion passed.

The board completed a nomination and vote to fill the vice‑president vacancy, approving Janet Bosco to the post. The meeting record shows all motions carried by voice vote; individual roll‑call tallies were not recorded in the transcript.

Procedural next steps: the contractor will remove and repour a short stretch of sidewalk to install the pad in a constrained area, and staff said they will schedule the staff in‑service day to coincide with the transformer cutover to minimize additional closures.