WSDOT to pursue progressive design‑build procurement; RFQ targeted in early July

Joint Oregon–Washington Interstate Bridge Replacement Joint Committee · June 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Washington State DOT and program staff said they plan a qualifications‑based progressive design‑build procurement with an RFQ aimed for early July, a fall RFP, selection in spring 2027 and construction start in 2028; staff emphasized independent cost estimating, an off‑ramp safeguard and small‑business goals.

John White, assistant secretary for urban mobility access and mega programs at WSDOT, described the program’s transition from planning to delivery and explained why staff plan to use a progressive design‑build procurement. White said the method allows the program to select teams based on qualifications, develop designs in collaboration with a contractor during a first‑phase engagement, negotiate pricing transparently and use an independent cost estimator to reconcile assumptions.

White described safeguards: an ‘‘off‑ramp’’ that would let the agency take the design and re‑procure work if negotiations fail, and contractual requirements for key personnel and small‑business subcontracting plans. He said staff expect to release a request for qualifications in early July (a July 6 target was cited) followed by a fall request for proposals, selection in spring 2027 and substantial construction work beginning in 2028.

Why it matters: Program staff argued progressive design‑build can speed delivery while allowing negotiation of better pricing and clearer sharing of risk. White also said consolidating bridge approaches and demolition into a single progressive design‑build package reduces contract coordination risks and oversight burdens.

Members’ questions and commitments: Legislators asked how small‑business and workforce goals will be enforced; White said the RFQ will include early signal language and the RFP will require subcontracting plans and key‑personnel commitments, and that staff will facilitate industry networking events. The program also said it has a vendor portal and engagement outreach for thousands of firms interested in participating.

Next steps: If approvals and the finance plan proceed as planned, staff said a phase‑1 negotiated design engagement could begin in 2027 and initial construction activities could start in 2028.