Greenwood council approves sidewalk change order, storm-sewer repairs and $38,000 budget amendment

Greenwood City Council · April 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved a change order to the 2024 sidewalk and curb maintenance project for additional full-panel replacements, authorized storm-sewer repairs with Redford Construction after a July 5 incident, and amended the FY2025 operating budget to add $38,000. Staff outlined timelines and funding sources.

The Greenwood City Council on a voice vote approved a series of routine infrastructure and budget measures, including a change order to the 2024 sidewalk and curb maintenance project, authorization for storm‑sewer repairs and a $38,000 amendment to the city’s FY2025 operating budget.

During discussion of Resolution R2024‑70 — a change order to the 2024 sidewalk and curb maintenance improvement project for the Boyatt Streetscapes — Administration staff explained that Foundation 1 assessed numerous sidewalk panels for polyjacking and identified several that are ineligible and must be replaced as full panels. "There’s some worn-out ADA paneling and some other cracks in panels," said Steven (Administration), noting photos of affected panels and that work would be funded from the contract’s force account, a previously approved contingency within the contract amount. Steven said roughly $16,000 would be used from that account to cover the additional replacements. The council approved the change order by voice vote.

The council also passed Resolution R2024‑72 to repair storm‑sewer corrugated metal pipe following an incident on July 5. Steven told the council staff solicited multiple bids and selected Redford Construction as the lowest bidder; Redford has about a two‑week lead time and the project could be finished in October. "We got multiple bids and staff decided on this bid," Steven said. The resolution was approved by voice vote.

On ordinances, the council advanced and passed Bill 2024‑73, amending the FY2025 operating budget to add $38,000 to the expenditure budget. Council members said the funds would cover an emergency repair. The motion carried by voice vote.

Why it matters: The measures authorize immediate repairs and minor budget adjustments to maintain city infrastructure and public safety. The sidewalk change order responds to safety and ADA concerns where polyjacking is not a viable option; the storm‑sewer work responds to a specific storm event and moves the repair into contractor scheduling.

What’s next: Staff will issue change orders and contracts as needed; Redford Construction expects a short lead time before mobilizing, and administration indicated the comprehensive‑plan recommendation and other department follow‑ups will return to the board at upcoming meetings.