Committee reviews revised salt-shed design; debates wall height and steel framing
Summary
Drafter Mark Cowdrey presented a shortened salt-shed design (depth reduced to 40 feet) with three bays and changes to roof pitch and walls. Committee members discussed concrete wall height (8' vs. 10'), steel framing for the front wall, bracing and footing concerns, and agreed to consult engineers and check DES permit progress.
Get email alerts on the Salt Shed Design topic
No spam. Unsubscribe anytime.
At the Oct. 16 Highway Building Advisory Committee meeting, drafter Mark Cowdrey presented revised plans for the town's salt shed, describing changes to bay widths, overall depth and structural details.
Cowdrey described three bays sized 14'9", 19'2" and 38'9" (rounded gross widths ~16', 20', 40') and said the depth had been reduced from 60' in earlier concepts to 40'. He noted additional buttresses on the back wall and described the roof pitch as "7' pitch on back and 6\" pitch on the front" in the minutes; committee members flagged that phrasing for confirmation with structural suppliers.
Committee member Bill MacDuffie, Jr. noted a prior discussion about an 8' concrete back wall and said a taller wall (about 10') would be preferable; Cowdrey confirmed the plan shows a 4' concrete wall above grade topped by 4' of timber, and that concrete thickness is shown as 10". Chair Jim Hoyt and members discussed metal beams for the front wall, metal siding, and the need for footings under steel beams; member Harvey Peters warned that if a beam were struck the building could be compromised, highlighting the tradeoffs between impact resistance and constructability.
Cowdrey emphasized the plans were conceptual and not structural, and that bracing and structural specifics should be finalized with builders and suppliers. The committee agreed to consult a concrete finisher and a structural engineer on bracing and beam footing questions and to contact Cheryl Bentley regarding the status of the DES permit.
Clarifying details recorded in the minutes include bay measurements, reduced depth and that the concrete wall is shown as 4' above grade plus 4' timber above that; committee members asked for verification of the roof pitch notation and recommended confirming buttress heights with a concrete finisher.
Next steps: the chair will follow up with technical consultants; the committee will verify permit status with Cheryl Bentley; meeting adjourned at 8:00 p.m.