Riverdale Park staff outline $89,000 bioretention project for Beale Circle funded by county grant

Riverdale Park Town Council (work session) · January 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said Prince George's County and Chesapeake Bay Trust awarded an $89,000 grant for a micro‑bioretention facility at Beale Circle West; design by on‑call engineer Pannoni is complete, county will supply/install trees with council approval, and staff will seek a task-order contract to start spring construction.

Town staff briefed the mayor and council on a county- and Chesapeake Bay Trust–funded bioretention project designed to improve water quality and reduce runoff from Beale Circle West.

Peaks described the facility as a "micro bioretention" area positioned to intercept stormwater from adjacent roadways and impervious surfaces; the scope includes minor regrading, planting a naturalized palette of native shrubs, grasses and perennials, and construction of an engineered stormwater treatment feature. Staff said on-call engineer Pannoni completed drainage analysis and design details and is reviewing construction proposals from the town’s on-call contractors.

The project’s CIP budget and grant amount is $89,000 with no town match; staff said approximately $70,000 remains after covering engineering costs and is expected to cover installation. Prince George’s County Department of the Environment will supply and install street trees contingent on mayor-and-council approval in fall 2026. Staff plan to ask the council at the next legislative meeting to authorize a task-order contract with the selected contractor, with construction expected in spring.

Council members asked about lane closures and timing; Director Lewis said material staging may close a lane temporarily during regrading but the roadway will remain open for traffic. Staff also committed to posting designs and images on the town website before construction.