Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Wastewater Treatment topic
No spam. Unsubscribe anytime.
Thorp council approves $54,023 pay request and $55,717 change order for wastewater plant; project pushed to June 2025
Summary
The City of Thorp approved Pay Application #20 and Change Order #10 for its wastewater treatment plant upgrade, authorizing $54,023.65 to Staab Construction and a $55,717 change order that extends the project to June 30, 2025; SEH reported the plant is 95.5% complete.
Get email alerts on the Wastewater Treatment topic
No spam. Unsubscribe anytime.
The City of Thorp on Dec. 9 approved two payments tied to its wastewater treatment plant upgrade and authorized a schedule extension after engineers said additional work remains.
Council members voted 5–0 to approve Resolution 2024-12-01, authorizing Pay Application #20 to Staab Construction Corporation for $54,023.65 (M/M/S Rosemeyer, Lawcewicz). The council later approved Resolution 2024-12-03 to accept Change Order #10 for $55,717 (M/M/S Korn, Lawcewicz); that motion passed 4–1 with Alderperson Abramczak voting against the change order.
Jerimiah Wendt of Short Elliott Hendrickson, the city’s project engineer, told the council the wastewater treatment plant is "95.5% complete," with ongoing punch-list work, site restoration and drained ponds at the south site for sludge removal. The change order includes driveway repairs with added gravel top dress, extending gravel to the riffraff and adding a concrete pad by the south lagoon; the council recorded a new completion date of June 30, 2025, citing required sludge removal.
The pay application and change order affect ongoing contractor payments to Staab Construction for the 2023 Wastewater Treatment Plant Upgrades Project. Alderperson Korn, who seconded the change-order motion, emphasized the work items in the change order; Alderperson Abramczak opposed the change order but the minutes do not record a public explanation of that vote.
The approvals keep the construction contract moving forward while the council and staff address remaining site-restoration items. The project’s next steps include completing punch-list items and final site grading before final acceptance.
Provenance: Topic introduced at SEG 016 (SEH project update) and the formal pay-application vote appears at SEG 021; the change-order discussion and vote are recorded at SEG 024–025.
Speakers cited: Jerimiah Wendt, Alderperson Rosemeyer, Alderperson Lawcewicz, Alderperson Korn, Alderperson Abramczak.
