Fireman’s Park paving fails proof roll; contractor to rework at about $16,600 extra

Parks, Recreation & Forestry Board of the Village of Slinger · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Slinger Parks, Recreation & Forestry Board was told the recent paving at Fireman’s Park failed a proof roll; Director Tony Dobson said the contractor must remove fill and bring fresh stone, adding just over $16,600 while the project remains under the $150,000 budget.

Tony Dobson, Parks, Recreation & Forestry Director, told the board on June 2 that the paving work at Fireman’s Park failed the contractor’s proof roll and must be redone.

Dobson said the contractor will haul out existing fill and bring in fresh stone, adding "just over $16,600" to the work. He said that even with the additional work, the project is expected to finish well under the initially budgeted $150,000; Dobson estimated total final project costs at around $64,000.

Dobson said crews planned to pave the parking lot the following day. Board members discussed but did not approve a proposed rustic trail from the parking lot to the restroom area, choosing instead to defer that decision until the board’s August meeting at Fireman’s Park.

The board recorded no formal motion tied to the extra cost at the meeting; Dobson presented the contractor’s corrective plan and a short-term schedule. The next procedural step is for staff to proceed with the contractor’s rework and report back at the August site meeting if further decisions are needed.