Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Master Plan And Flood Control topic

No spam. Unsubscribe anytime.

Parish president unveils Iberia Parish master plan outreach and highlights multi‑hundred‑million flood projects

Iberia Parish Council · July 8, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Iberia Parish President told the council the parish has begun its first master plan and is advancing multiple flood‑control projects with CPRA partners, including Delton Canal (~$180M) and a commercial canal (~$150M); council members also approved major subdivision plats by Guidry Land Development LLC totaling 189 units.

Iberia Parish leaders on July 8 urged residents and council members to participate in the parish’s first comprehensive master plan and updated the council on large flood‑control projects and local development proposals.

The Parish President described the master plan as “the first real master plan that we’ve done in Iberia Parish,” urged council members to attend two scheduled briefings and encouraged the public to submit survey responses and photos of local flooding. He said administration is working with Royal Engineering on alternative analyses for several flood‑control reaches and is coordinating projects with the Coastal Protection and Restoration Authority (CPRA).

During his remarks the president cited preliminary cost estimates discussed with engineers: he described the Delton Canal project at about $180,000,000 and a commercial canal at about $150,000,000, and said model and environmental work is underway with an alternative‑analysis phase expected to finish by the end of the month. He said the parish is pursuing CPRA funding and other sources to leverage those large projects.

Council members also reviewed multiple planning items from the Regional Planning Commission. A significant approval granted preliminary and final plat to Guidry Land Development LLC to subdivide roughly 62.2 acres into 76 residential lots, 3 commercial lots and 2 apartment lots, yielding a total of 189 dwelling units. Council discussion focused on drainage analysis and lighting compliance; a planning representative told members they received two constituent contacts with concerns and that the developer would comply with subdivision rules and staff conditions.

The Parish President and council members framed the Guidry project as an economic-growth opportunity; during discussion council members estimated the academy and related investments could total tens of millions of dollars (one figure cited: ~$25,000,000 for the academy and a broader development package reaching roughly $80,000,000 when combined with other projects). Members noted potential infrastructure needs (wastewater, roads, drainage) tied to such growth.

The parish is also promoting a notification system called Iberia PINs for emergency alerts and updates, and advertised current openings in parish government and an upcoming exit audit presentation. The council approved the planning items and moved the master plan and canal projects forward for continued study and later action.

Next steps: Royal Engineering will complete the alternative analysis; planning staff will monitor developer compliance with subdivision conditions; the master-plan outreach events are scheduled for the week following the meeting.