Jones County accepts low bid from Shiv Construction for Highway 49 Phase 5; board approves award
Summary
The board accepted Shiv Construction’s low bid for Highway 49 Phase 5 and approved an award that includes a ductile‑iron alternate, revising the recommended contract to roughly $3.0 million; staff said ARPA and county bond funds will cover the work.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Jones County commissioners voted July 7, 2026, to accept Shiv Construction’s low bid and award the contract for Highway 49 Phase 5, an ARPA‑funded infrastructure project.
Public works staff (speaker 15) told the board six contractors submitted bids and Shiv Construction was the low bidder at $2,000,006.48. Staff recommended acceptance of the base bid and an alternate to use ductile‑iron pipe on parts of the route; including that alternate, staff said, would revise the contract to $3,000,005.83. Staff said a portion of the work would be paid from remaining ARPA funds and the balance from county bond proceeds.
Commissioners asked about the project’s progress and tie‑ins; staff said phases 2 and 4 are complete and testing was imminent. A commissioner moved to accept the low bid and include the alternate; the motion was seconded and approved by voice vote.
Why it matters: the award advances completion of a multi‑phase water/road project identified in the county’s ARPA plan. Staff said the county has remaining ARPA funds and bond capacity available to cover the revised contract amount.
What’s next: contracts were expected to be prepared for signature later in the week and staff said work would continue on testing and completing remaining phases.