Bethel Park SD says new elementary school on track for Sept. 1; change orders and staffing adjustments noted
Summary
District project presenter reported that Bethel Park Elementary’s site and interior finishes are nearing completion, with a target opening of Sept. 1; inspectors are scheduled mid‑August and moving is set for Aug. 3–18. The board reviewed change orders including a $22,000 glazing credit and ongoing negotiations over electrician supervision costs.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Presenter gave a progress update on the new Bethel Park Elementary School, saying the district expects 'All areas will be open for September 1 to start school.' Photos shown to the board displayed sidewalks, permanent paving, exterior window detailing and final landscaping.
The presenter said interior work is progressing: ceiling components and painting are underway in the LGI, wall finishes are mostly complete, epoxy flooring is being installed in the kitchen and serving areas, carpet is laid in the media room and flooring work has begun in the cafeteria. He highlighted specialty finishes, including a 'Starry Night' tunnel feature, and reported the project has logged 41 days without a recordable injury and one recordable incident to date.
On schedule, the presenter said final inspections were set to begin the week of Aug. 17, moving was planned for Aug. 3–18, and staff would be able to access rooms after inspections with a reported staff reporting date of Aug. 26. 'We set the date of the 17th for inspections to get the published date,' the presenter said when describing the inspection and occupancy sequence.
The board reviewed several change orders. The presenter described change order GC‑59, a revision to the storefront glazing related to ASI 4/RFI 317; the revision was made for constructability and joinery reasons and produced a roughly $22,000 credit to the district. He also explained staffing changes for the electrician trade: the contractor ran multiple crews without additional charge to the district but required added supervision, which the district previously compensated for on an earlier change order and is reconciling for later months. The presenter said he was still negotiating deductive change orders with Rycon to offset some costs and that the amounts proposed 'do still fall under the change order that's left,' but that those negotiations were not yet final.
Board members asked whether the roughly $200,000 left in contingency covered the listed items; the presenter confirmed the page‑two amounts did not exceed the remaining change order balance but emphasized the final reconciliation was pending. A facilities lead moved the change orders to the consent agenda for approval.
The presenter closed by thanking the board; no public comments were offered during or immediately after the presentation. The district will proceed with mid‑August inspections, scheduled move dates and final reconciliation of pending change orders before final occupancy.