Utah Life Steamers seek kiosk, temporary storage and $1M master plan for Shea Park
Summary
At a work session the volunteer Utah Life Steamers presented a master plan for Shea Park that includes a permanent engine house, steaming bays, a pavilion and a history kiosk; the club asked council staff to help advance a kiosk and short-term storage solution while council raised parking, code and vandalism concerns.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
The Utah Life Steamers urged Saratoga Springs’ City Council on June 16 to support a phased upgrade of Shea Park that would add a permanent engine house to store locomotives and equipment, steaming bays for club members, a small pavilion and a historical kiosk. The presentation came in a council work session; no final council action was taken, but staff was directed to work with club representatives on next steps.
Club liaison Eric Nielsen said the group has engaged an architect and can fund a kiosk immediately. “We do have the money to purchase the materials and to build this and to put it out at the park,” Nielsen said, describing a two-sided kiosk that would explain the site’s railroad history on one face and club events and fundraising details on the other.
The Steamers showed conceptual elevations that also included an engine house and a decorative water tower intended to give the area a historic rail theme; the full master plan was estimated by the club at roughly $1,000,000. As an interim measure the club asked permission to place a 20-foot Connex container—camouflaged with a mural or siding—to store donated equipment that cannot be transported each event. Club representatives estimated a container would cost about $3,000 and said they would seek to make it more visually appealing and temporary.
Council and staff focused on operational and policy details: parking impacts during peak events, code and permitting for a storage container, vandalism risk, maintenance responsibility after an MOU or donation, and the need for an MOU that would clarify that any built improvements become city property. Council members asked staff to examine parking options, a possible sunset provision for temporary storage, and a phasing plan so high-priority items (the kiosk and temporary storage) can proceed before permanent construction.
Staff member Mark (city staff) said the city could prioritize a kiosk and temporary storage while working through code, MOU and phasing questions and noted that the Connex placement could be sited near the proposed permanent building footprint so it can be removed when construction begins.
What the club asked for - Council to allow staff to work with the Steamers on a phasing plan and MOU. - Permission to place a temporary storage container with aesthetic treatments and a short sunset if necessary. - Support for a kiosk funded and built by the club to showcase railroad history and post event information.
Why it matters Shea Park is a high-traffic community amenity; formalizing storage and a permanent facility would reduce logistics burdens on volunteers, allow longer operating hours and potentially expand educational offerings. Council members repeatedly flagged parking as a constraint and asked for staff analysis before a formal approval.
What’s next Council assigned council members Waddemann and Wilson to meet with staff and the club on one-off discussions; staff will review code, potential MOU language, timeline and parking options and return with recommendations for a future work session or agenda item.