Killeen unveils draft ADA self‑evaluation and 20–30 year transition plan with estimated costs
Summary
City staff and consultants presented a draft Americans with Disabilities Act self‑evaluation and transition plan that inventories barriers and sets a multi‑decade schedule for remediation. Staff estimated roughly $6.4M for facility upgrades (20 years) and about $267M for public‑rights‑of‑way work (30 years); adoption is expected at the July 21 meeting.
Get email alerts on the Accessibility topic
No spam. Unsubscribe anytime.
City staff and consultant STV presented the draft Americans with Disabilities Act (ADA) self‑evaluation and transition plan at the July 7 meeting, summarizing community engagement, the inventory of accessibility barriers, timelines, and cost estimates for remediation.
The plan reflects input gathered during public meetings, a focus group and an online survey. It divides work into priorities and phases, and proposes a long‑term program for facilities and public rights‑of‑way. Staff presented estimated remediation costs: roughly $6.4 million to correct accessibility barriers in city facilities over a minimum 20‑year timeline, and an estimated $267 million to bring public rights‑of‑way (sidewalks, curb ramps, crossings) into full ADA conformance over a 30‑year timeframe. Staff and the consultant emphasized that many right‑of‑way upgrades can be paired with roadway capital projects and that grants (including Safe Routes and other transportation grants) are often appropriate funding sources.
The draft plan is a federal requirement following a 2021 settlement with the Department of Justice; staff said the document is a living plan and will be updated as projects proceed. Staff will return July 21 with a final draft for council consideration and requested that council consider adoption in late July.
What happens next: staff will incorporate council and public comments into a final draft and seek formal adoption at the July 21 meeting and pursue grant opportunities to accelerate right‑of‑way work where feasible.