Board delays further approvals for Keren Hatorah until septic system re-inspection and conditions met

Town of Thompson Planning Board · April 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Planning Board declined to grant further approvals to Keren Hatorah pending re-inspection and verification of the septic system and resolution of outstanding conditions; the applicant said inspections will occur during summer use and is addressing site cleanup and ramp repairs.

Joel Kohn, project representative for Keren Hatorah, told the Board that MHE review comments have been received and that the septic system will require a re-inspection while the facility is in use during the summer. Kohn said the owners hired a company to clean up the site and intend to address outstanding building violations.

Board members and staff emphasized that the project must comply with the original approval, complete all septic inspections, and resolve outstanding conditions before receiving any additional approvals. Jim Carnell said several building permit applications have been submitted; consulting attorney Steve Vegliante said he reviewed the PUD law and bylaws and advised the Board that it has performed due diligence but that both existing and proposed community buildings must be open to the entire community, not restricted to one religion or demographic.

The Board determined it was not comfortable issuing further approvals until the septic system has been approved by the town engineer and prior conditions have been met.