Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Red River Valley Water Supply topic

No spam. Unsubscribe anytime.

Officials brief Grafton council on Red River Valley Water Supply Project, request commitments

City of Grafton City Council · November 4, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Representatives of the Garrison Diversion Conservancy District and consultant AE2S briefed the council on the Red River Valley Water Supply Project, asking for Memorandums of Commitment by January and noting the project is pursuing federal funds.

Duane DeKrey, general manager of the Garrison Diversion Conservancy District, and Shawn Gadde of engineering firm AE2S presented the Red River Valley Water Supply Project to the City Council on Nov. 4. They described the effort as a State project intended to provide long‑term emergency supply, supplement inadequate existing surface waters, and support future economic growth. They said project leaders are seeking federal funding and asked local governments to provide Memorandums of Commitment by January to document interest and potential participation.

DeKrey and Gadde reviewed the project plan and costs, and told the council that the Public Utilities Commission will discuss the matter in December. They emphasized that being “in” the project would help guarantee a stable, reliable water supply and support economic development; the minutes record those benefits but do not detail funding commitments or specific cost shares for Grafton.

Council members did not record a formal vote on participation at this meeting; the presenters asked for commitments and indicated additional action would be considered as the project moves through state and federal review.