Michiana council approves water contract with Michigan City, moves forward on grant-funded water-main work

Village of Michiana Council · August 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Village of Michiana approved a water contract with Michigan City and heard a timetable for a grant-funded water-main project tied to a $620,000 grant; the council voted unanimously on the contract Aug. 9.

The Village of Michiana council approved a water contract with Michigan City at its Aug. 9 meeting, moving forward with planned repairs and a grant-funded water-main project.

Council President Brian Cassidy moved to approve the contract and Council Member Mike Mumper seconded; the motion passed on a 3–0 roll call vote. Council Member Mike Mumper said a new pump will be installed after Labor Day and that Merritt Engineering is finalizing plans for a water project on Creek that is part of a $620,000 grant.

Mumper said the water-main portion of the project is expected to take two to three weeks once crews begin, with asphalt restoration possible by mid-November. The council did not set a final start date at the meeting but discussed aiming to begin work in October, contingent on permitting and contractor scheduling.

The contract approval formalizes the village’s arrangement with Michigan City for water service or related operations described in the motion; council members did not enumerate additional contract terms during the public meeting. Resident Jurate asked for clarification on the water contract during public comment; council members indicated staff would follow up with details.

The council also approved related routine items during the meeting, including minutes and the check register. The contract vote was recorded as 3 ayes, 0 nays.