Cecilton reviews WWTP report, orders pump to keep system online
Summary
The council heard a July wastewater and water-supply report from John Neddo; two meter pumps were ordered and staff plan to buy one SPR pump and rebuild the other to avoid extended outages.
Get email alerts on the Utilities Wwtp topic
No spam. Unsubscribe anytime.
The Town of Cecilton Mayor and Council received a July report on the town’s wastewater treatment plant and water supply during its Aug. 17 meeting.
John Neddo reviewed the plant’s month, calling it "a pretty good month." He told the council that Treasurer Roland assisted in ordering two meter pumps to be installed, and staff are working on the discharge pumps. Council was told that one SPR pump may be offline at a time; the plan is to purchase one new pump and send the other out for rebuilding to maintain continuous operation.
No budget amendment or formal vote to approve purchases was recorded in the minutes; Treasurer Roland’s assistance in ordering the equipment was noted during the report. The council took no further formal action in the meeting minutes on contracting or capital expenditure approvals.