Appling County outlines expanded road projects and TIA budget revision as LMIG paving planned
Summary
In August the county recognized Roberts Civil Engineering as Engineer of Record, issued notices to proceed for 2023 LMIG paving (bid $2,123,077.37) and revised the TIA budget from $2.72M to $3.098M (additional funds $377,225); county staff listed priority projects and available funding sources including ARPA and 2018 SPLOST overages.
Get email alerts on the Roads And Projects topic
No spam. Unsubscribe anytime.
At a work session on Aug. 24, Appling County leaders outlined a stepped-up schedule for road and capital projects, clarified engineering oversight and detailed available funding sources.
Roberts Civil Engineering was recognized as Engineer of Record and issued notices to proceed for previously approved 2023 LMIG and TIA projects. The county reported the 2023 LMIG paving bid amount of $2,123,077.37 and planned paving to begin in October. Separately, the 2024 LMIG application submitted to the state requests roughly 9.202 miles of patching, leveling and resurfacing on Pat Lewis Road, Lamar Crosby Road and Old Surrency Road.
The county’s TIA program budget was revised from an original $2,720,828 to $3,098,053 after approval of additional funds totaling $377,225 to cover inflation and revised costs. Commissioners approved the revised TIA budget at a regular meeting following notice of additional state funding for specific road segments (Nails Ferry Road and Ten Mile Road).
Staff presented several specific project proposals for discussion or bid advertising, including Sunshine Drive, Old Field Cemetery Road (pending property-owner agreements), Crosby Chapel paving, Aquatic Center parking (estimated quote $139,999), replacement bleachers at the tractor-pull area (estimated $335,000), concession-stand repairs, Ag Center pen modifications and a county barn funded from 2018 SPLOST allocations. Reported funding sources include American Rescue Plan funds ($1,680,616), TSPLOST ($2,824,197), 2023 LMIG ($1,051,992) and 2018 SPLOST infrastructure funds (estimated $2,435,698), with projected 2018 SPLOST overages to be split 74% county/26% city.
Why it matters: The revised TIA budget and planned LMIG paving represent a significant near-term capital work plan that will affect county roads, project timelines for contractors and the county’s fiscal allocations across multiple funding sources.