Commission recommends $85,000 design contract for South Pond dredging; approves $10,000 budget amendment
Summary
The Middleton Water Resources Commission voted to recommend awarding a design contract to MSA for South Pond dredging and approved a $10,000 amendment to the project budget to cover higher design costs.
Get email alerts on the Infrastructure Dredging topic
No spam. Unsubscribe anytime.
The Water Resources Commission recommended that the city accept MSA’s proposal to provide design services for South Pond dredging at a cost not to exceed $85,000 and approved a $10,000 budget amendment to cover the difference from the carried line item.
Staff member (speaker 3) told the commission that only one proposal was received for the dredging design and that the bid came in roughly $10,000 higher than the amount the city had previously carried in its budget. "The proposal came in about 10,000 over what our budget was," the staff member said, adding that the carried budget figure had been in place for one or two years.
Committee member (speaker 5) moved to recommend acceptance of MSA’s proposal for $85,000; a colleague (speaker 1) seconded the motion. The commission then approved the recommendation by voice vote with no members recorded as opposed.
Commission members also moved and approved a separate budget amendment to increase the applicable line item by $10,000 so the finance office will see an $85,000 allocation when it processes the design agreement.
The staff presentation noted that the $85,000 figure covers engineering services to design the dredging and not the physical dredging work itself; the design will support a future competitive procurement of the dredging contract. Staff also said the city has a separate capital improvement project (CIP) that could consider a later South Pond expansion, but the current action is strictly for design to restore the existing pond footprint.
The motion is a recommendation to finance and counsel; final authorization to contract will occur when those bodies review and approve the agreement.
The commission scheduled further budget and CIP discussion in next month’s meeting packet, where staff will present details on funding and any potential scheduling changes.