Board approves bidding for 38th Place stormwater work and reissues County Line culvert bid
Summary
The authority approved advertising bids for Phase 1 and 2 of the 38th Place stormwater project (estimated about $5.3 million with contingency) and concurrently reissued bid documents for the County Line culvert project to align schedules.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The board voted to advertise and solicit bids for Phase 1 and 2 of the 38th Place/Filmore stormwater improvement project and to reissue bid documents for the County Line culvert project so both procurements can run concurrently.
Staff said Phase 1 and 2 are currently estimated at about $5.3 million including a 15% contingency; earlier bonding had been sized at roughly $6 million. The board discussed separating phases for bidding but decided to run the larger Phase 1–2 package with the County Line culvert procurement occurring at the same time to achieve efficiencies and attract competitive pricing.
Moderator (S3) explained the schedule: advertise in local papers, hold a pre‑bid conference, open bids in early May and seek award at the May 12 board meeting. Staff said the pre‑bid conference will be at the municipal offices and noted some permits (DNR) and right‑of‑entry issues remain to be secured for outfalls and easements.
Board members asked for clarity on whether culvert replacement under the railroad would be done in phases or as a single emergency replacement; staff said Phase 3 (railroad crossing) may require separate permitting and could be phased depending on cost and railroad coordination.
The motion to proceed with advertising and reissuing bid documents passed on a voice vote. Staff will return with bid results and recommended award.