Authority declares emergency for failing Old Ridge Road culvert, seeks immediate proposals
Summary
The board declared an emergency after staff described a severely deteriorated culvert on the 300 block of Old Ridge Road and authorized solicitation of emergency engineering and construction proposals.
Get email alerts on the Infrastructure Emergency topic
No spam. Unsubscribe anytime.
The Hobart City Redevelopment Authority voted to declare a public‑safety emergency for a failing culvert on the 300 block of Old Ridge Road after field staff described a large sinkhole and extensive corrosion in a corrugated metal pipe.
Field staff described the culvert as heavily corroded and partially collapsed, with scour on both banks and a void that created a sinkhole next to the sidewalk. Moderator (S3) told the board the condition posed a safety and drainage risk and recommended immediate action. The board unanimously approved a motion to declare an emergency and to solicit emergency proposals for engineering and construction to address the culvert.
Moderator (S3) said staff had a preliminary site report and recommended using the engineering firm that had already been onsite for a rapid plan and cost estimate. Staff committed to obtain proposals quickly so the board could review options at the next meeting or call a special session if needed.
The board’s action authorizes staff to solicit emergency proposals for engineering and construction work; no contract was awarded at the meeting. The board’s recorded motion was moved and seconded during the meeting and approved by voice vote.
Next steps identified by staff include refined engineering evaluation by the on‑site consultant, preparation of a scope and cost estimate, outreach to impacted property owners, and coordination with traffic plans if the work must be staged near the roadway. The board emphasized the work’s urgency and directed staff to return with proposals and estimated timelines.