Board approves building and dredging permits, adopts boat‑measurement motion and tables wake study until lake repairs are complete
Summary
The Board approved three building applications and three dredging requests contingent on permits and commission conditions, adopted a boat‑measurement rule for a specific 2024 Skeeter, and voted to table a wake study until Cordry returns to normal pool following dam repairs.
Get email alerts on the Permits And Regulation topic
No spam. Unsubscribe anytime.
The Cordry‑Sweetwater Board approved several land‑use and operational items on Aug. 20, including contingent approval of three building applications and three dredging requests, a motion establishing measurement points for a specific 2024 Skeeter watercraft, and a motion to table an updated wake study until Cordry Lake returns to normal pool after dam repairs.
Building Commission chair Pat Sherman moved to approve building applications 24‑060, 24‑062 and 24‑064 contingent on lot owners obtaining all Brown County permits and meeting Building Commission conditions; the motion passed unanimously after staff confirmed one dock location had been surveyed. Sherman also moved to approve dredging requests D024‑009, D024‑010 and D024‑011 conditional on Building Commission requirements; that motion also passed unanimously.
On boat measurement, the Board debated manufacturer length versus a measured length while a boat is on plane; Mr. Parris moved to define measurement points for the 2024 Skeeter (from a defined forwardmost hull point, excluding rub rail, to the rearmost running part of the hull while on plane) and to approve the specific boat if it measured under CSCD rules. The motion passed unanimously; counsel noted prior work on a formal resolution to change measurement methodology and cautioned about conflicting motions.
On the wake study, several Board members and freeholders said conducting the study while Cordry is lowered for dam repairs could produce inaccurate results; the Board unanimously tabled the wake study until the lake is at normal pool to preserve study validity, while acknowledging that delay may require requesting a new proposal later because pricing could change.
What happens next: Building and dredging approvals proceed contingent on county permits and Building Commission conditions; staff will return with refined boat‑measurement procedures and guidance at a future meeting; the wake study remains on hold until lake levels are restored.