Fenton committee approves $92,750 in concrete additions for city ball fields
Summary
The committee approved Change Order #2 to add concrete at high‑traffic park locations—including 846 square yards of ball-field concrete totaling $88,900 and table footings—intended to eliminate recurring mud and maintenance issues following heavy use.
Get email alerts on the Park Infrastructure topic
No spam. Unsubscribe anytime.
The Board of Aldermen Committee approved Change Order #2 on April 9 to add concrete at several problem areas in Fenton City Park, including 846 square yards of ball‑field concrete at $105 per square yard ($88,900) and four table base footings (total $3,850).
Staff and contractor R.V. Wagner proposed concreting the areas between softball/baseball Field 1 and Field 2 and behind Field 3’s backstop to address settled gravel areas that form standing water after heavy rain and cannot sustain grass under heavy league and tournament traffic. Staff said these areas have repeatedly caused maintenance problems and that grading and grass repairs have been ineffective.
Alderwoman Robin Huels moved to approve the change order; Alderman Jimmy Lange seconded and the committee approved the expenditures unanimously. The work will be added to the existing 2026 Park Concrete Replacement contract and brought to the Board as a formal change order for ratification.