Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the School Facilities topic

No spam. Unsubscribe anytime.

Wentworth council approves two contracts for Wentworth Consolidated School repairs

Town of Wentworth Town Council · October 1, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council unanimously approved a $29,445.53 Stonewall Construction quote for entrance/double-door work and a $12,500 contract to refinish the gym floor, after clarifying a 'P&O' line item on the estimate.

The Wentworth Town Council approved two contracts Tuesday to address repair and refinishing work at Wentworth Consolidated School.

Mayor Dennis Paschal Jr. presented two bids: Stonewall Construction’s Project 6 for the front entrance and installation of ADA double doors at $29,445.53, and a $12,500 quote from contractor Clint Yokley to sand and refinish the gym floor, paint lines, and apply two coats of sealant.

Councilmember Cheryl Moore asked about a 'P&O @ 12%' line on the Stonewall estimate. Councilmember Dennis Paschal III said he searched online and reported that 'P&O' stands for 'Profit and Overhead,' a contractor line item to cover time and expenses. The minutes note a prior estimate from Elmer Galloway of about $5,000 to sand the floor and $2,000 to paint lines; the current quotes replace those earlier figures.

Mayor Paschal moved to approve both items under the school repairs agenda entry; Mayor Pro Tem Evelyn Conner seconded and the motion carried unanimously.

The minutes incorporate the proposed improvement plans as part of the meeting documentation; no financing contingency or additional conditions were recorded.